When a roof is replaced, every skylight gets one of three answers. Reflash a sound, newer unit with new flashing. Replace a unit that is old, fogged, cracked or a yellowed plastic dome. Or remove it and frame the opening in. A reroof is the cheapest moment for any of the three, because the roofing around the skylight is coming off anyway.
This guide is about that decision. If a skylight is leaking now, the skylight leaks section of our roof repair page explains how a roofer tells a flashing leak from a failed unit.
Reflash, replace or remove: how to decide
| What you see | Usual answer at reroof time | Why |
|---|---|---|
| Newer glass unit, clear, no stains around the shaft | Reflash: new flashing kit and underlayment, unit stays | The unit is sound; new flashing goes in with the new roofing |
| Fogging or streaks between the panes that don’t wipe off | Replace | VELUX reads this as a failed seal |
| Cracked glass or frame, or a stained light well | Replace | Cracks and stains mean water or moisture is getting past the unit |
| Old acrylic or plastic bubble dome, cloudy or yellowed | Replace with a glass unit | VELUX lists discoloration, mildew stains, leaks and condensation as signs a bubble skylight is due |
| A skylight you no longer want, or one in the way of solar panels | Remove and frame in | Simplest while the roof is open; needs framing, sheathing and insulation |
Whatever the row, the flashing gets a decision too. Oregon’s reroofing rules say existing flashings, vents and similar parts of the roof assembly must be replaced where they are rusted, damaged or deteriorated, and that flashings are rebuilt to the maker’s instructions (R908.5 and R908.6 in the 2023 Oregon Residential Specialty Code). For a VELUX skylight that stays, new flashing is also a warranty condition, as the next section explains.
Should skylights be replaced when you replace the roof?
VELUX’s answer is yes, if they are getting old. Its guide to skylight replacement says many of its skylights last 20 years or more, suggests upgrading after about 30, and calls a reroof one of the best times to replace them because it saves time and lines up the skylight and roofing warranties. The signs it lists are the ones in the table: leaks, cracks, yellow stains around the opening and condensation trapped between the panes. Every VELUX unit carries a data plate on the frame with its model, glass type and date of manufacture, which settles the age question quickly.
The warranty point matters most at reroof time. VELUX’s own explanation of its warranty (May 2026) lists, among the things it does not cover, re-roofing without re-wrapping the skylight in VELUX adhesive underlayment and VELUX flashing. So a VELUX skylight that stays through a reroof should get a new matching flashing kit and underlayment, not the old flashing and a bead of sealant. Other makers have their own terms; ask the roofer to read them before the bid.
A note on age: these figures are a maker’s own estimates. A skylight’s real condition, and whether its glass still meets current energy rules (below), matter more than its birthday.
Curb-mounted or deck-mounted skylights?
Most residential skylights are one of two kinds, and the difference decides how a replacement goes in.
| Deck-mounted | Curb-mounted | |
|---|---|---|
| How it sits | Fastened directly to the roof deck, close to the roofing | Set on a raised frame, the curb, built on the roof around the opening |
| Roof slope (VELUX) | 3:12 and steeper; not for low slopes | Flat to 20:12 |
| Typical use | New roofs and full replacements | Flat and low-slope roofs, and replacing older skylights |
| VELUX flashing for shingles | EDL kit | ECL kit |
Sources: VELUX’s mounting and flashing guide and skylight FAQ, read October 10, 2026. VELUX also sells self-flashed units, with the flashing built in, for low slopes.
The residential code adds one rule: a unit skylight on a roof flatter than 3:12 must sit on a curb at least 4 inches above the roof, unless the maker’s instructions say otherwise (R308.6.8 in chapter 3 of the 2023 code). On a flat or low-slope roof a curb is the normal answer.
On an ordinary pitched Portland roof the choice is open, and it comes down to the opening. VELUX pitches its curb-mounted units at replacing older skylights, since a new unit can be sized to sit on the existing curb. Switching to a deck-mounted unit gives a lower profile, but the curb comes off and the new frame has to suit the opening, work that is easiest with the roofing already stripped. Either way, the roofer measures before ordering: VELUX’s FAQ asks for the width and length of the unit where the shingles meet the flashing, the height of the skylight or curb, and the size of the opening inside.
Flashing kits and the maker’s instructions
A skylight is only as watertight as the layers around it. VELUX’s explanation of its flashing describes three:
- The unit’s own seal. On a deck-mounted skylight a deck seal is nailed to the roof; a curb-mounted unit has a gasket between curb and skylight.
- Adhesive underlayment. Strips of self-adhering membrane run over the deck seal and up the sides of the unit, or wrap the whole curb.
- The flashing kit. A sill flashing at the bottom, step flashing woven in with each course of shingles up the sides, and a saddle and head flashing across the top, interwoven with the roof underlayment.
The kit has to match both the skylight and the roof. VELUX pairs its deck-mounted units with an EDL kit on shingles, an EDM kit designed for ribbed or standing seam metal, and an EDW kit on tile, so a skylight in a metal roof needs a different kit from one in composition shingles.
Oregon’s code makes flashing at roof openings a requirement (R903.2.1), and it exempts unit skylights from the cricket that any other penetration wider than 30 inches must have, but only where the skylight meets the glazing rules of R308.6 and is flashed to the maker’s instructions (R903.2.2). In other words, the instructions are part of the code compliance, not a suggestion.
Two things worth putting in the bid: which flashing kit, by name, goes on each skylight, and who flashes it. VELUX’s FAQ notes that some roofers prefer to install skylights, or at least flash them, so that the shingles and flashing around them meet the roofer’s own warranty terms.
Glazing, energy rules and the NFRC label
A replacement skylight is new glazing in an existing house, and both states’ energy codes reach it.
- Oregon. The state’s own energy chapter sets a maximum U-factor of 0.50 for skylights in its prescriptive table, and says alterations that affect energy components must meet the chapter (Table N1101.1(1) and N1101.2.1 in the 2023 Oregon amendments). Every window, and the chapter counts skylights as windows, must carry an NFRC-certified label that lists its U-factor and stays on until the inspector has seen it (N1104.4.1).
- Washington. The state energy code requires replacement fenestration to meet its U-factor and solar heat gain table, which allows skylights a U-factor of 0.50 in Clark County’s climate zone (WAC 51-11R, R503.1.1.1 and Table R402.1.3), with U-factors rated to NFRC 100.
Lower is better for U-factor, a measure of heat loss through the whole unit, frame included. The label also gives the solar heat gain coefficient and the visible transmittance, the share of daylight that gets through. The Department of Energy’s buying guidance for windows, doors and skylights and ENERGY STAR’s criteria both start from the NFRC rating, so it is the number to compare between quotes.
Safety glazing is a separate rule. Oregon’s code limits skylight glazing to laminated glass, fully tempered or heat-strengthened glass, wired glass or approved rigid plastics, and requires a screen under tempered or heat-strengthened glass in many cases (R308.6.2 to R308.6.5); laminated glass used as the inner pane needs no screen. Unit skylights must be tested and labeled to the AAMA/WDMA/CSA 101/I.S.2/A440 standard (R308.6.9).
One Portland caution about winter drips. VELUX explains that condensation forms when warm, moist air from the house meets a cold skylight, and its warranty treats it as the result of indoor humidity, not a leak, and excludes it. A new unit does not change how damp the house air is. If drips form on the inside in winter, the roof ventilation guide explains where that moisture comes from.
Do you need a permit to replace a skylight?
Not always, and no source we found answers it for skylights by name.
- Oregon. The state’s permit exemptions, in force since October 1, 2026, include door and window replacements, except where a structural member is changed (R105.2, item 14, in the 2026 Chapter 1). The list does not mention skylights.
- Portland. The City’s permit guidance lists replacing doors or windows without widening or shrinking the opening as no-permit work, and cutting, widening or reducing an opening as permit work. It does not mention skylights either.
- Clark County. The County requires a permit to replace any windows, and a re-roofing permit for every building, per its residential permits page.
So a same-size swap during a reroof may need nothing, while a bigger opening, a new skylight or a closed-off one changes the roof framing, which both the state list and Portland treat as permit work for windows. Ask Portland Permitting & Development, your suburb’s building department or, across the river, Clark County or the City of Vancouver (see the Vancouver page). The roof permit guide has the rules for the reroof itself.
Removing a skylight you no longer want
Closing a skylight is partly framing work, not just roofing. A wide skylight usually sits in an opening where rafters were cut and headed off; even a narrow one leaves a hole in the deck. Filling it means framing to carry the deck where needed, new sheathing level with the roof around it, and then underlayment and roofing laid straight across. Inside, the light well is closed and the ceiling patched, and the new section of ceiling is insulated: Oregon’s energy chapter applies to alterations that affect the parts of the house it regulates, so the patch should be insulated like the ceiling around it.
Because the structure changes, check the permit question above before the roofer prices it. It is still far simpler during a reroof than at any other time, because the roofing on that part of the roof is coming off regardless.
Skylights and solar panels on the same roof
If panels are going on, or back on, after the reroof, plan the two together. Oregon’s code says a solar array must not be placed where it would restrict the function of skylights, vents or drains (R324.6.5), and a skylight in the middle of the sunniest plane can cost panel space. If one sits where panels would go, the reroof is the time to decide whether it stays, is replaced or is closed off. The guide to replacing a roof with solar panels covers the rest of that job.
What does skylight replacement cost?
We publish no price for it, because we have found no Portland source that states one. VELUX’s FAQ gives national ranges by type of skylight, including interior and exterior finish work, and notes that the height and pitch of the roof, the mount type and the complexity of the job all move the figure. On our roof replacement cost page, the Cost vs. Value rows price one standard project that includes two skylights in a full tear-off, which is a reminder that skylights are an ordinary line on a reroof bid.
Ask for each skylight to be priced separately on the bid, with:
- the decision for that unit: reflash, replace or remove;
- the replacement model, its mount type and its NFRC U-factor;
- the flashing kit by name, and who installs it;
- any work inside: light-well drywall, paint, trim.
The roof replacement page lists what else a full replacement bid should spell out. To describe your roof and its skylights, use the request form. Before you hire anyone, check the roofer’s license on the Construction Contractors Board’s search in Oregon, or their L&I registration in Washington.
This page is general information, not professional advice about your specific situation. Have it assessed by a qualified professional before making decisions. Last reviewed October 10, 2026.